As a commercial software vendor, it is EXTREMELY important to maintain a SCHEDULE and deliver software on the date that we communicate to the market that the software will be released. This is critical because we have existing customers who pay software maintenance and expect on a regular basis:
1. bug fixes
2. minor feature improvement/enhancements to existing features
3. resolutions to any workflow issues they may have reported
4. new features at major releases
It is also critical to deliver new major features to the market to enable the sales force to meet the demand of the feature in the market on time to capture the sale! If you deliver the feature 1 year after another software vendor has already released the equivelent feature, you put your sales force at a disadvantage as they are playing catch-up against the competition.
ERDAS targets two releases per year (a minor release in Q1 and a major release in Q4).
It is far too easy to get trapped in "release date creep" in an Agile Software Development Methodology. There are several reasons for this...
1. The very nature of the methodology is user experience driven, not software architectural by nature like a waterfall methodology
2. It is easy to "not" do architecture or take the "big picture" into account before implementing a use cases. This sometimes leads to the inclusion of "technical debt" into the software by the final implementation not "fitting" into a holistic architecture of the software. This results in the need to refactor the software at a later time to "clean up" the architecture and/or create harmony across similar use cases.
3. The use case may be implemented, but the resulting performance and non functional requirements were not accounted for...only the ability of the use case to be met by the actor in the system was focused upon. For example, the use case works on Oracle, but not PostGreSQL, or the use case works in IE6, but not Firefox.
In short, the analysis of "what it will take to implement a use case" process when planning a sprint can be a difficult process on very large feature sets and feature sets that span multiple tiers of the software (i.e. Database, Server, Middleware, Clients).
In previous blog posts, I mentioned our own software development teams use of the "Spike" in our methodology to "flush out" technical unknowns and document architectural requirements before implementing use cases. This process in the Agile Methodology has been a great tool to our development teams.
Besides technically flushing out architecture and technology before implementing use cases, it's important to take a step back and look at the release cycle as a whole and the stages of the release cycle to ensure that the software meets not only the user experience, but the non functional categories of quality, performance and OS/DB/App Server needs.
Rather than develop the use cases "just in time" on a sprint by sprint basis, our Product Management Teams develop all the use cases for a release cycle BEFORE the release cycle begins. This allows the development team to understand the system under design as a whole and also for the Product Management teams to clearly and concisely present to the development teams what we expect the system actors to be able to accomplish when the software is released. Building a "Release" backlog of use cases really enables the development teams to consider architectural dependent use cases, understand the software as a whole and choose appropriate technology to meet all of the use cases, not just incorporate technology at run time during sprints.
We also provide ample time at the end of the release cycle for software stabilization (bug and improvement issues that provide quality to the software and ensure the software meets performance and the non functional requirements). Completion of the new features and stabilization signifies a "Feature Complete" state of the software, where the teams agree that the software could be released to the market.
We're still not "done" at that point!! The software goes through a final QA which it must pass to be released to the market, Acceptance Testing and BETA and then finally if AT and BETA does not reveal any critical bugs, the software goes into a box and is delivered to the market.
In short, if you are new to the Agile Methodology, MAKE A DATE that you expect the software to be released, MAKE A PLAN that adequately will enable your development team to meet that date and MAKE ROOM to test the quality and performance of the software BEFORE releasing it to the market!
Subscribe to:
Post Comments (Atom)
3 comments:
Hi, your blog is really impressive. Thanks for sharing such a nice article.
The IT market is also following the same pattern. The ideas like delegate application growth and offshore application growth took beginning and found lifestyle due to the mixture of the best possible quality product at aggressive prices.
Great share! Thanks for the information. Keep posting!
Post a Comment